We’re on a somewhat tight deadline for this project, as I promised Carol that the house would be completed in time for us to have our stuff moved in and have Thanksgiving dinner at our place this year. For that to happen, the house has be COMPLETELY finished by the Monday before Thanksgiving – November 17, 2014.
Below is the schedule we need to adhere to in order to make that happen. And here is a formal version thanks to one of my readers:
I’ll be updating the schedule as we progress through the project…
Planned Dates | Component/Task | Status |
---|---|---|
Pre-Construction | Surveys | COMPLETED SEPTEMBER 2013 |
Pre-Construction | Variance | COMPLETED NOVEMBER 2013 |
Pre-Construction | Architectural Drawings | COMPLETED MARCH 2014 |
Pre-Construction | Environmental/Site Plans | COMPLETED MAY 2014 |
Pre-Construction | Asbestos Removal | COMPLETED MAY 2014 |
Pre-Construction | Permits | COMPLETED JUNE 19, 2014 |
Pre-Construction | Sediment Control | COMPLETED JUNE 17, 2014 |
June 16 | Porta Potty | COMPLETED JUNE 19, 2014 |
June 16-17 | Demo | COMPLETED JUNE 19, 2014 |
June 16 – July 6 | Excavation | COMPLETED JUNE 20, 2014 |
June 16 – July 6 | Foundation – Footers | COMPLETED JUNE 25, 2014 |
June 16 – July 6 | Foundation – Walls | COMPLETED JUNE 30, 2014 |
June 16 – July 6 | Plumbing – Ground Work | COMPLETED JULY 1, 2014 |
June 16 – July 6 | Foundation – Termite Pre-Treat | COMPLETED JULY 3, 2014 |
June 16 – July 6 | Foundation – Waterproofing | COMPLETED JULY 1, 2014 |
June 16 – July 6 | Foundation – Slabs/Flat Work | COMPLETED JULY 18, 2014 |
July 7-27 | Backfill | COMPLETED JULY 11, 2014 |
July 7-27 | Framing – Basement | COMPLETED JULY 22, 2014 |
July 7-27 | Framing – First Floor | COMPLETED JULY 22, 2014 |
July 7-27 | Framing – Second Floor | COMPLETED JULY 23, 2014 |
July 7-27 | Framing – Roof Trusses | COMPLETED JULY 25, 2014 |
July 7-27 | House Wrap | COMPLETED JULY 29, 2014 |
July 7-27 | Framing – Stairs/Interior | COMPLETED JULY 29, 2014 |
July 7-27 | Install Windows | COMPLETED JULY 30, 2014 |
July 7-27 | Install Exterior Doors | COMPLETED JULY 30, 2014 |
July 7-27 | Framing – Back Deck / Porch | COMPLETED JULY 29, 2014 |
July 28 – August 24 | Roof | COMPLETED JULY 28, 2014 |
July 28 – August 17 | Water Meter Installation | COMPLETED JULY 28, 2014 |
July 28 – August 17 | Main Water Line Installation | COMPLETED AUGUST 4, 2014 |
July 28 – August 17 | Sewer Installation | COMPLETED AUGUST 4, 2014 |
July 28 – August 17 | Rough HVAC | COMPLETED AUGUST 15, 2014 |
July 28 – August 17 | Rough Plumbing | COMPLETED AUGUST 13, 2014 |
July 28 – August 17 | Rough Electrical | COMPLETED AUGUST 18, 2014 |
July 28 – August 24 | Rear Deck/Porch Trim | COMPLETED OCTOBER 22, 2014 |
July 28 – August 24 | Siding – Vinyl | COMPLETED OCTOBER 3, 2014 |
N/A | Siding – Stone | N/A |
July 28 – August 24 | Gutters | COMPLETED OCTOBER 6, 2014 |
August 18-24 | Sprinklers | COMPLETED AUGUST 15, 2014 |
August 25-31 | Insulation – Walls | COMPLETED AUGUST 21, 2014 |
August 25-31 | Insulation – Attic | COMPLETED OCTOBER 16, 2014 |
September 1-7 | Sheetrock Installation | COMPLETED AUGUST 25, 2014 |
September 8-14 | Sheetrock Finishing | COMPLETED SEPTEMBER 1, 2014 |
September 8-28 | Driveway | COMPLETED NOVEMBER 18, 2014 |
September 8-28 | Walk-Ways | WILL WAIT UNTIL SPRING |
September 15-28 | Hardwood Installation | COMPLETED SEPTEMBER 10, 2014 |
September 15-28 | Install Cabinet/Vanities | COMPLETED OCTOBER 3, 2014 |
September 15-28 | Interior Doors | COMPLETED SEPTEMBER 16, 2014 |
September 15-28 | Carpentry / Trim | COMPLETED OCTOBER 3, 2014 |
September 29 – October 5 | Garage Door / Opener | COMPLETED OCTOBER 8, 2014 |
September 29 – October 12 | Interior Painting | COMPLETED OCTOBER 4, 2014 |
October 13-19 | Exterior Painting | WILL WAIT UNTIL SPRING |
October 13-26 | Finish Electrical | COMPLETED NOVEMBER 7, 2014 |
October 13-26 | Finish Plumbing | COMPLETED OCTOBER 28, 2014 |
October 13-26 | HVAC Trim-Out | COMPLETED OCTOBER 29, 2014/td> |
October 21 – November 2 | Roof Leaders | COMPLETED OCTOBER 6, 2014 |
October 21 – November 2 | Bio-Retention Pond | COMPLETED NOVEMBER 6, 2014 |
October 28 – November 2 | Countertops | COMPLETED OCTOBER 24, 2014 |
October 28 – November 2 | Tiling – Floors/Showers | COMPLETED OCTOBER 10, 2014 |
October 28 – November 2 | Carpet Installation | COMPLETED OCTOBER 31, 2014 |
November 3-9 | Hardwood Finishing | COMPLETED NOVEMBER 24, 2014 |
November 3-9 | Appliances | COMPLETED NOVEMBER 25, 2014 |
November 3-16 | Final Grading | COMPLETED NOVEMBER 18, 2014 |
November 3-16 | Landscaping | COMPLETED NOVEMBER 19, 2014 |
November 3-16 | Fence | NOT YET STARTED |
November 10-16 | Punch List / Touch-Ups | COMPLETED NOVEMBER 21, 2014 |