We’re on a somewhat tight deadline for this project, as I promised Carol that the house would be completed in time for us to have our stuff moved in and have Thanksgiving dinner at our place this year. For that to happen, the house has be COMPLETELY finished by the Monday before Thanksgiving – November 17, 2014.

Below is the schedule we need to adhere to in order to make that happen. And here is a formal version thanks to one of my readers:

Initial Schedule

I’ll be updating the schedule as we progress through the project…

Planned Dates Component/Task Status
Pre-Construction Surveys COMPLETED SEPTEMBER 2013
Pre-Construction Variance COMPLETED NOVEMBER 2013
Pre-Construction Architectural Drawings COMPLETED MARCH 2014
Pre-Construction Environmental/Site Plans COMPLETED MAY 2014
Pre-Construction Asbestos Removal COMPLETED MAY 2014
Pre-Construction Permits COMPLETED JUNE 19, 2014
Pre-Construction Sediment Control COMPLETED JUNE 17, 2014
June 16 Porta Potty COMPLETED JUNE 19, 2014
June 16-17 Demo COMPLETED JUNE 19, 2014
June 16 – July 6 Excavation COMPLETED JUNE 20, 2014
June 16 – July 6 Foundation – Footers COMPLETED JUNE 25, 2014
June 16 – July 6 Foundation – Walls COMPLETED JUNE 30, 2014
June 16 – July 6 Plumbing – Ground Work COMPLETED JULY 1, 2014
June 16 – July 6 Foundation – Termite Pre-Treat COMPLETED JULY 3, 2014
June 16 – July 6 Foundation – Waterproofing COMPLETED JULY 1, 2014
June 16 – July 6 Foundation – Slabs/Flat Work COMPLETED JULY 18, 2014
July 7-27 Backfill COMPLETED JULY 11, 2014
July 7-27 Framing – Basement COMPLETED JULY 22, 2014
July 7-27 Framing – First Floor COMPLETED JULY 22, 2014
July 7-27 Framing – Second Floor COMPLETED JULY 23, 2014
July 7-27 Framing – Roof Trusses COMPLETED JULY 25, 2014
July 7-27 House Wrap COMPLETED JULY 29, 2014
July 7-27 Framing – Stairs/Interior COMPLETED JULY 29, 2014
July 7-27 Install Windows COMPLETED JULY 30, 2014
July 7-27 Install Exterior Doors COMPLETED JULY 30, 2014
July 7-27 Framing – Back Deck / Porch COMPLETED JULY 29, 2014
July 28 – August 24 Roof COMPLETED JULY 28, 2014
July 28 – August 17 Water Meter Installation COMPLETED JULY 28, 2014
July 28 – August 17 Main Water Line Installation COMPLETED AUGUST 4, 2014
July 28 – August 17 Sewer Installation COMPLETED AUGUST 4, 2014
July 28 – August 17 Rough HVAC COMPLETED AUGUST 15, 2014
July 28 – August 17 Rough Plumbing COMPLETED AUGUST 13, 2014
July 28 – August 17 Rough Electrical COMPLETED AUGUST 18, 2014
July 28 – August 24 Rear Deck/Porch Trim COMPLETED OCTOBER 22, 2014
July 28 – August 24 Siding – Vinyl COMPLETED OCTOBER 3, 2014
N/A Siding – Stone N/A
July 28 – August 24 Gutters COMPLETED OCTOBER 6, 2014
August 18-24 Sprinklers COMPLETED AUGUST 15, 2014
August 25-31 Insulation – Walls COMPLETED AUGUST 21, 2014
August 25-31 Insulation – Attic COMPLETED OCTOBER 16, 2014
September 1-7 Sheetrock Installation COMPLETED AUGUST 25, 2014
September 8-14 Sheetrock Finishing COMPLETED SEPTEMBER 1, 2014
September 8-28 Driveway COMPLETED NOVEMBER 18, 2014
September 8-28 Walk-Ways WILL WAIT UNTIL SPRING
September 15-28 Hardwood Installation COMPLETED SEPTEMBER 10, 2014
September 15-28 Install Cabinet/Vanities COMPLETED OCTOBER 3, 2014
September 15-28 Interior Doors COMPLETED SEPTEMBER 16, 2014
September 15-28 Carpentry / Trim COMPLETED OCTOBER 3, 2014
September 29 – October 5 Garage Door / Opener COMPLETED OCTOBER 8, 2014
September 29 – October 12 Interior Painting COMPLETED OCTOBER 4, 2014
October 13-19 Exterior Painting WILL WAIT UNTIL SPRING
October 13-26 Finish Electrical COMPLETED NOVEMBER 7, 2014
October 13-26 Finish Plumbing COMPLETED OCTOBER 28, 2014
October 13-26 HVAC Trim-Out COMPLETED OCTOBER 29, 2014/td>
October 21 – November 2 Roof Leaders COMPLETED OCTOBER 6, 2014
October 21 – November 2 Bio-Retention Pond COMPLETED NOVEMBER 6, 2014
October 28 – November 2 Countertops COMPLETED OCTOBER 24, 2014
October 28 – November 2 Tiling – Floors/Showers COMPLETED OCTOBER 10, 2014
October 28 – November 2 Carpet Installation COMPLETED OCTOBER 31, 2014
November 3-9 Hardwood Finishing COMPLETED NOVEMBER 24, 2014
November 3-9 Appliances COMPLETED NOVEMBER 25, 2014
November 3-16 Final Grading COMPLETED NOVEMBER 18, 2014
November 3-16 Landscaping COMPLETED NOVEMBER 19, 2014
November 3-16 Fence NOT YET STARTED
November 10-16 Punch List / Touch-Ups COMPLETED NOVEMBER 21, 2014

{ 0 comments… add one now }

Leave a Comment