Week 13 Schedule

by J Scott on September 8, 2014

Last week was pretty slow, but we got done everything we had planned. Monday was a holiday, but on Tuesday we finished sheetrock, on Wednesday we primed all the walls and on Friday we started laying hardwoods. The walls look great, and the hardwood that’s already gone in looks great as well. We didn’t get the garage door installed yet, but it’s on order.

Here are the tasks scheduled for the week:

  1. Finish Hardwood Installation: On Monday and Tuesday, we’ll finish the hardwood.
  2. Install Trim: The rest of the week will be spent installing trim around the house, including baseboards, casing, crown molding, etc.

Should be a pretty easy week!