We had a great week last week, and we accomplished most of what we set out to accomplish. The new water and sewer lines went in, HVAC rough-in most completed, plumbing rough-in got about two-thirds of the way completed, we finished interior punch-out for the framing, and we even started on the back deck, front porch and the electrical rough-in.
The goal of this week will be to complete mechanicals and electric rough-in, as well as sprinkler rough-in and all associated inspections.
Here is what we’re looking like in terms of detailed schedule for this week:
- Sprinkler Rough-In: By Tuesday, I’m expecting sprinkler rough-in will have started and I’m hoping we’re completed by Thursday.
- HVAC Rough-In: By Tuesday, I’m hoping HVAC rough-in will be be completed.
- Plumbing Rough-In: By Tuesday, I’m hoping plumbing rough-in will be be completed.
- Electrical Rough-In: By Thursday, I’m hoping electrical rough-in will be be completed.
- HVAC Rough Inspection: By Friday, I’m hoping we’ve passed our HVAC rough inspection.
- Electrical Rough Inspection: By Friday, I’m hoping we’ve passed our electrical rough inspection.
- Plumbing Rough Inspection: By Friday, I’m hoping we’ve passed our plumbing rough inspection.
- Sprinkler Rough Inspection: By Friday, I’m hoping we’ve passed our sprinkler rough inspection.
- Deck & Porches: By Friday, I’m hoping the front deck and the rear deck/porch are completed. This includes the front columns, the screened porch and all the decking and trim.
If we can complete all our rough-in work this week, that would put us back on schedule. Then, the hope would be to get our framing inspection early next week and start/finish insulation next week as well, putting us a week ahead of schedule. Either way, I’m very happy with the progress we’ve been making!